AssetPipe / AssetCity / Incident queue
LIVE MK

Incident queue

All operational issues — open, in progress, resolved. P1 first.
1
P1 emergencies
avg TTA 4 min
1
P2 urgent
in progress
1
P3 standard
open
4
Resolved 24h
MTTR 4.2h
266
Residents impacted
cumulative last 7d
P1 INC-2026-0117 BH-002 pressure dropping open
Borehole BH-002 flow dropped to 1.8 m³/h from nominal 4.0.
BH-002 Hydro Boreholes Pvt Ltd 47 affected Opened 17 May 15:48
P2 INC-2026-0116 GATE-SOUTH motor service overdue in progress
Service was due 3 days ago. Spare motor in stores. Scheduling for tomorrow morning before peak resident movement.
GATE-SOUTH Powertech Solutions Opened 17 May 14:00
P3 INC-2026-0115 Perimeter PIR · Block C · false alarm cluster open
Three triggers in 12 min, no visual confirmation on CCTV review. Likely cat or windblown debris.
PERIM-NORTH SecureGuard 24 Opened 16 May 23:00
P2 INC-2026-0114 ZESA Stage 4 load shedding extended resolved
Generator activated at 14:00, ran for 5h 47m. ZESA restored 19:47. No service interruption to residents. Diesel burn 38L.
GEN-100 Powertech Solutions 247 affected Opened 17 May 12:00 · resolved 17 May 14:47
P4 INC-2026-0113 Sewage pump trip · reset successful resolved
SEW-PUMP-1 tripped on overload. Reset, ran 20 min test, OK. Booking inspection for next week.
SEW-PUMP-1 EcoPump Systems 18 affected Opened 17 May 10:00 · resolved 17 May 10:40
P3 INC-2026-0112 Smart bin BIN-B1 reported 92% full · early collection resolved
Bin filled faster than schedule (likely large event in Phase 2 plaza). Dispatched GreenClean early.
BIN-B1 GreenClean Waste Opened 16 May 14:00 · resolved 16 May 15:00
P2 INC-2026-0111 Stand 178 anomalous water usage resolved
Stand 178 usage 380L in 24h (typical 90L). Possible leak. Resident notified, plumber dispatched.
WM-101 Hydro Boreholes Pvt Ltd 1 affected Opened 15 May 16:00 · resolved 15 May 22:00

Detail